Project

Five Weeks, Not Twelve: Tribal Transportation Program

Location

Hollywood, Big Cypress, Brighton and Immokalee reservations, FL

TEC Role

Prime consultant: on-call engineering, project management and CEI

Riprap embankment repair on a Seminole Tribe of Florida roadway
Seminole Tribe of Florida transportation project
Seminole Tribe of Florida transportation project

About The Project

The Challenge

The Tribe needed one firm to design, permit and inspect transportation work across four reservations: roundabouts, resurfacing, drainage, driveway rehabilitation, street lighting and signage. All of it had to meet FDOT standards and Tribal regulations. Then extreme weather washed out a roadway embankment, creating an immediate safety risk.

What We Did

We produced plans, hydraulic calculations and permit packages, with approvals from FDOT, the County and Tribal Environmental offices. We managed construction with daily photo reports, pay-requisition review, QA/QC testing and MOT oversight.

For the washout, we investigated the site and had designs ready in under five days. We then wrote the bid package, ran the contractor selection and managed the repair, using geofabric slope pinning and riprap. On the roundabout, we measured the intersection, resized the geometry and cut excess MOT.

Results

  • The embankment repair was finished in five weeks instead of the typical eight to twelve.
  • Bid participation on the roundabout rose from 50% to 75%.
  • The Tribe also got an erosion-control BMP manual, an FDOT-based Traffic-Calming Guide and weekly CIP dashboards.

Services: Project Management · CEI · Roundabout Design · Drainage · Emergency Repairs · Permitting · Program Controls