Every TEC project is public civil infrastructure for a city, county, state agency, federal agency or tribal government, delivered through the same QA/QC process every time. Where we worked as a subconsultant, we say so.

Client

City of North Miami

Project

Banyan Pump Station Rehabilitation & Owner’s Engineer Services

Location

North Miami, FL

TEC Role

Prime consultant, Owner’s Engineer Representative

Original access hatch in the roadway at the Banyan Pump Station, North Miami
Old access hatch removed at the Banyan Pump Station
Crew replacing the access hatch at the Banyan Pump Station
New watertight, traffic-rated access hatch delivered to the Banyan Pump Station

About The Project

The Challenge

The Banyan duplex wet-well pump station had been damaged by a vehicle and placed under a Miami-Dade DERM moratorium. It had been on bypass for four years. At the same time, the City needed an owner’s representative across more than 20 active capital projects.

What We Did

We treated Banyan as an emergency rehabilitation. We surveyed the site, modeled the hydraulics and prepared a complete permit set, then secured DERM approval for flood-resilient retrofits, including a watertight, traffic-rated access hatch. We prepared the construction documents, supported procurement, and carried the job through construction QA/QC and closeout, photo-documenting the access hatch replacement before, during and after construction.

Across the City’s capital program, we ran the weekly CIP tracker and reviewed scopes, plans, permits and pay applications. We delivered full CEI on the NE 126th Street parking improvements, logged more than 100 FPL and County streetlight repair tickets in a GIS tracker with bi-weekly progress calls, and led an Advanced Metering Infrastructure (AMI) assessment with compliance matrices and 10-year life-cycle models.

Results

  • Banyan came out of a four-year bypass and went back into service.
  • NE 126th Street finished on time and on budget.
  • The City cleared a large streetlight backlog and got a 10-year roadmap for advanced metering.
  • CIP tracking and QA/QC became standard across Public Works.